New Construction

New Construction Isn’t Finished: What I Find Before the Warranty Runs Out

Home › Blog › New Construction & 11-Month Inspections

“It’s brand new. Why would I need an inspection?” I hear it every week. Here’s what brand new looked like on a few recent Metro Detroit builds.

Roof-to-wall flashing installed wrong

Macomb new build. From the drone, the lower roof where it meets the upper-story wall had flashing problems: nail heads exposed in the top shingle course, metal flashing left exposed with surface sealant and exposed fasteners, and a cut shingle piece loose and not lapped under the flashing. That intersection is exactly where water gets behind siding. Nobody’s going to see it from the driveway.

Drone photo of a lower roof meeting an upper-story wall on a new build, showing improperly installed step flashing
Lower roof meeting the upper wall. From the ground, you’d never know.

Plumbing resting on wiring, and a sump line that sprays

Same house: a PVC pipe was resting on electrical cables in the basement ceiling near the main panel. And when the sump pump ran, the discharge piping sprayed water. A sump pump that wets the basement is working against itself.

PVC drain pipe resting directly on electrical cables in a new construction basement ceiling, circled in red
PVC pipe resting on the electrical cables.
New sump pump pit and discharge pipe in a new construction basement
The sump pump. The discharge piping sprayed water when it ran.

A porch with no guardrail

Detroit new build, final inspection. Raised front porch, no guardrail. Steps not installed at a secondary exterior door. Gutters missing. The furnace condensate drain leaking onto the basement floor. A garbage disposal that didn’t run.

Raised front porch on a new build with no guardrail, the open edge marked in red
Raised porch, open edge, no guardrail.
Furnace condensate drain line leaking onto a basement floor, red arrow pointing to the leak
Furnace condensate drain leaking at the floor.

And the one that still gets me: 130.3°F water out of the kitchen tap in a house a week from closing, with every smoke alarm still wearing its construction dust cover.

Why this happens

Builders have a lot of trades moving through a lot of houses on a tight schedule. The city inspector checks code minimums, quickly. The builder’s walkthrough is the builder grading their own homework. I work for you, and I give your house all day if it needs it.

The three times to look

  1. Pre-drywall. Framing, rough plumbing, electrical and mechanicals while the walls are still open. Once the drywall goes up, it’s gone.
  2. Final, before the walkthrough. Book it a day or two before the builder’s walkthrough so you walk in holding the list.
  3. 11 months. Most builders’ workmanship warranty runs about a year. Check your paperwork for the exact terms. After a year of living in it, settling, a full heating season and a summer, things show up: drywall cracks, doors out of adjustment, grading that settled toward the house, roof and flashing issues. Get the list to the builder before the warranty runs out, while it’s still theirs to fix.

My take

New doesn’t mean done. It means nobody’s lived there long enough to find out. A builder correction list in your hands, on their time, is the best deal in real estate.

Building or bought new in Macomb or Oakland County?

Pre-drywall from $249. New construction final from $349. 11-month builder warranty inspection from $349. Drone roof flight (airspace and weather permitting), attic camera and targeted FLIR thermal scan on every one.

Book online 586-522-8733

— KyleKyle Winn · Owner & Inspector · PreFlight Home Inspections · 586-522-8733

☎ Call Book Online